Update on Route 74 Paving Project as of July 19, 2016

The plan as it stands right now:
Belden Excavating will start ditching next week.  They may start at the Shoreham end of Route 74, or they may start at the Cornwall end.  There will be flaggers and most likely delays once this process starts.  You might want to think about an alternate route.
Wilk Paving is scheduled to begin paving on August 9. They will start be shimming the Cornwall end of the road, and then move to the Shoreham end. The pavers will return to put on a finish coat after all the shimming has been completed.  The paving must be finished by September 24, but it is expected that it will finish much sooner than that.
I will let you know if I receive any further updates.